NEW QUESTION 20
Which of the following is not the reason why the NetCol 8000-A infrared humidifier water tray is not filled with water?

  • A. The water injection pipe is blocked
  • B. Infrared lamp damage
  • C. Inlet line valve is not open
  • D. The water pressure is abnormal

Answer: B

 

NEW QUESTION 21
UPS2000-G-(6-20kVA) battery discharge time is significantly lower than the standard time may be caused by what? (Multiple choice)

  • A. No mains input
  • B. Increased load
  • C. Battery capacity reduction
  • D. The battery is not full

Answer: B,C,D

 

NEW QUESTION 22
Three sets of 9Ah battery packs are connected in parallel and connected to UPS2000-G-6kVA. What is the battery capacity set?

  • A. 27Ah
  • B. 18Ah
  • C. 32Ah
  • D. 9Ah

Answer: A

 

NEW QUESTION 23
The user can modify the login password in the ( ) menu of the ECC800 web interface.

  • A. Electronic label
  • B. User Management
  • C. System upgrade
  • D. Version information

Answer: B

 

NEW QUESTION 24
The alarm management functions supported by the ECC800 are (). (Multiple choice)

  • A. Alarm data export
  • B. Alarm parameter setting
  • C. View historical alarms
  • D. Filtering alarms

Answer: A,B,C,D

 

NEW QUESTION 25
In the case of normal mains, the UPS battery in inverter mode may be executed ( ). (Multiple choice)

  • A. Checking the capacity test
  • B. Shallow discharge test
  • C. Float charging
  • D. Balanced charging

Answer: A,B,C,D

 

NEW QUESTION 26
When the UPS is parallel, it is necessary to check the input phase sequence of each UPS main bypass, but the output phase sequence is not required.

  • A. FALSE
  • B. TRUE

Answer: A

 

NEW QUESTION 27
When the UPS5000-E (), boot will automatically run the Quick Setup Wizard. (Multiple Choice)

  • A. Start after recovery failure
  • B. The device is turned on again after the factory settings are restored.
  • C. Turn it off and then on.
  • D. First boot

Answer: B,D

 

NEW QUESTION 28
If the customer load cannot be de-energized, pay attention to ( ) when disconnecting the maintenance bypass switch after the repair is completed.

  • A. Battery input is normal
  • B. EPO status can be broken maintenance switch
  • C. The road module has no abnormal alarm and can be powered.
  • D. The maintenance bypass switch can also be disconnected when the bypass module is abnormal.

Answer: C

 

NEW QUESTION 29
The reason for using the EPO status interface in the parallel step of the UPS5000-E is ().

  • A. Prevent electric shock and protect personal safety
  • B. Protect the battery from discharge
  • C. Power off the load to prevent damage to the load device
  • D. Cut off the output and set the parallel parameters

Answer: D

 

NEW QUESTION 30
Which of the following air conditioning systems need to be equipped with a cooling tower or dry cooler?

  • A. Direct ventilation air conditioning system
  • B. CW air-cooled type
  • C. DX air-cooled type
  • D. DX water-cooled type

Answer: D

 

NEW QUESTION 31
To use the NetEco APP on PAD to query the PUE information of the current computer room, you need to click the () menu.

  • A. Alarm
  • B. More
  • C. Energy consumption
  • D. Monitoring

Answer: C

 

NEW QUESTION 32
In the NetCol5000-A air conditioner, if a large number of air bubbles are observed in the liquid crystal mirror, it indicates that the refrigerant system lacks refrigerant, and the refrigerant should be charged as needed.

  • A. True
  • B. False

Answer: A

 

NEW QUESTION 33
Two different versions of the software UPS2000-G can be implemented in parallel.

  • A. FALSE
  • B. TRUE

Answer: A

 

NEW QUESTION 34
How many NetCol5000-C water-cooled line-class precision air conditioners can be supported by one NetCol520 chilled water distribution unit?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: A

 

NEW QUESTION 35
In () setting interface, you can set the linkage rule of the multi-function sensor and the sunroof.

  • A. WiFi management
  • B. PLC
  • C. Version information
  • D. Access control user management

Answer: B

 

NEW QUESTION 36
In the "Video" function of NetEco, you can perform operations such as (). (Multiple Choice)

  • A. Video live browsing
  • B. Create a camera
  • C. Modify the camera
  • D. Delete the camera

Answer: A,B,C,D

 

NEW QUESTION 37
() can realize the signal processing and centralized control of UPS5000-E.

  • A. Energy Control Module ECM
  • B. Bypass module
  • C. Maintenance bypass module
  • D. Power module

Answer: A

 

NEW QUESTION 38
Which of the following is supported by the AI/DI port on the access control actuator?

  • A. Fingerprint reader
  • B. IC card reader
  • C. Open the button
  • D. Electronic magnetic lock

Answer: C

 

NEW QUESTION 39
In the battery model 6-GFM-150, 150 indicates the battery ().

  • A. Minimum capacity
  • B. Maximum capacity
  • C. Rated capacity
  • D. Actual capacity

Answer: C

 