Latest H12-421 Exam Real Tests Free Updated Today
H12-421 Real Exam Question Answers Updated [Jan 27, 2022]
NEW QUESTION 20
Which of the following is not the reason why the NetCol 8000-A infrared humidifier water tray is not filled with water?
- A. The water injection pipe is blocked
- B. Infrared lamp damage
- C. Inlet line valve is not open
- D. The water pressure is abnormal
Answer: B
NEW QUESTION 21
UPS2000-G-(6-20kVA) battery discharge time is significantly lower than the standard time may be caused by what? (Multiple choice)
- A. No mains input
- B. Increased load
- C. Battery capacity reduction
- D. The battery is not full
Answer: B,C,D
NEW QUESTION 22
Three sets of 9Ah battery packs are connected in parallel and connected to UPS2000-G-6kVA. What is the battery capacity set?
- A. 27Ah
- B. 18Ah
- C. 32Ah
- D. 9Ah
Answer: A
NEW QUESTION 23
The user can modify the login password in the ( ) menu of the ECC800 web interface.
- A. Electronic label
- B. User Management
- C. System upgrade
- D. Version information
Answer: B
NEW QUESTION 24
The alarm management functions supported by the ECC800 are (). (Multiple choice)
- A. Alarm data export
- B. Alarm parameter setting
- C. View historical alarms
- D. Filtering alarms
Answer: A,B,C,D
NEW QUESTION 25
In the case of normal mains, the UPS battery in inverter mode may be executed ( ). (Multiple choice)
- A. Checking the capacity test
- B. Shallow discharge test
- C. Float charging
- D. Balanced charging
Answer: A,B,C,D
NEW QUESTION 26
When the UPS is parallel, it is necessary to check the input phase sequence of each UPS main bypass, but the output phase sequence is not required.
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION 27
When the UPS5000-E (), boot will automatically run the Quick Setup Wizard. (Multiple Choice)
- A. Start after recovery failure
- B. The device is turned on again after the factory settings are restored.
- C. Turn it off and then on.
- D. First boot
Answer: B,D
NEW QUESTION 28
If the customer load cannot be de-energized, pay attention to ( ) when disconnecting the maintenance bypass switch after the repair is completed.
- A. Battery input is normal
- B. EPO status can be broken maintenance switch
- C. The road module has no abnormal alarm and can be powered.
- D. The maintenance bypass switch can also be disconnected when the bypass module is abnormal.
Answer: C
NEW QUESTION 29
The reason for using the EPO status interface in the parallel step of the UPS5000-E is ().
- A. Prevent electric shock and protect personal safety
- B. Protect the battery from discharge
- C. Power off the load to prevent damage to the load device
- D. Cut off the output and set the parallel parameters
Answer: D
NEW QUESTION 30
Which of the following air conditioning systems need to be equipped with a cooling tower or dry cooler?
- A. Direct ventilation air conditioning system
- B. CW air-cooled type
- C. DX air-cooled type
- D. DX water-cooled type
Answer: D
NEW QUESTION 31
To use the NetEco APP on PAD to query the PUE information of the current computer room, you need to click the () menu.
- A. Alarm
- B. More
- C. Energy consumption
- D. Monitoring
Answer: C
NEW QUESTION 32
In the NetCol5000-A air conditioner, if a large number of air bubbles are observed in the liquid crystal mirror, it indicates that the refrigerant system lacks refrigerant, and the refrigerant should be charged as needed.
- A. True
- B. False
Answer: A
NEW QUESTION 33
Two different versions of the software UPS2000-G can be implemented in parallel.
- A. FALSE
- B. TRUE
Answer: A
NEW QUESTION 34
How many NetCol5000-C water-cooled line-class precision air conditioners can be supported by one NetCol520 chilled water distribution unit?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: A
NEW QUESTION 35
In () setting interface, you can set the linkage rule of the multi-function sensor and the sunroof.
- A. WiFi management
- B. PLC
- C. Version information
- D. Access control user management
Answer: B
NEW QUESTION 36
In the "Video" function of NetEco, you can perform operations such as (). (Multiple Choice)
- A. Video live browsing
- B. Create a camera
- C. Modify the camera
- D. Delete the camera
Answer: A,B,C,D
NEW QUESTION 37
() can realize the signal processing and centralized control of UPS5000-E.
- A. Energy Control Module ECM
- B. Bypass module
- C. Maintenance bypass module
- D. Power module
Answer: A
NEW QUESTION 38
Which of the following is supported by the AI/DI port on the access control actuator?
- A. Fingerprint reader
- B. IC card reader
- C. Open the button
- D. Electronic magnetic lock
Answer: C
NEW QUESTION 39
In the battery model 6-GFM-150, 150 indicates the battery ().
- A. Minimum capacity
- B. Maximum capacity
- C. Rated capacity
- D. Actual capacity
Answer: C